CMC Markets
Data Cabling for new Offices and Data Centre
Location
133 Houndsditche, London, EC3A 7BX
Systems
Nexans Cat6 Copper & OM3 Fibre, Rittal TS8 Cabinets, CPI Patch Frames
Start & Finish
May 2010 – October 2010
Project Description
The project involved installing 4,500 Nexans LANmark-6 Cat6 outlets over three floors, terminated on CPI Patch Frames within the SER’s and 3-way/4-way GOP boxes at the floor end.
In parallel, Able Data built a new Data Centre, housing 70x Rittal server cabinets with the cabling brought back to 22x CPI Patch Frames.
Image Gallery
Download ![]() | Date | Notes |
|---|---|---|
| CMC Markets | Aug 11 | 285 KB |
Dedicated software is required to view PDF files. Your computer may already have PDF viewing software installed; it may have been included with your Web browser or operating system. If you do not have it already, you will need to download and install the PDF viewing software of your choice in order to view the PDF files on this site. | ||