Fidelity Investments

Summary
Cabling of Fidelity's Date Centres

Systems
Avaya SYSTIMAX GigaSPEED XL Cat6,
Avaya SYSTIMAX LazrSPEED OM2, OM3 

Project Description
In three separate projects, Able Data have cabled Fidelity's London based Data centres. In the first project Able Data supplied and installed thirty data cabinets and the required cabling infrastructure. The initial installation of 4,000 copper links was completed within four weeks. All RJ45 patch panels are of the Avaya Fleximax variety, where standard outlet modules are clipped into the panel.

The second and third projects were similar, but on a larger scale. The third project at Global Switch involved 10,000 links, installed over a period of one month, made possible by the use of off site pretermination,

As part of the initial project, Able Installed also 1,000 10Gbit OM2 fibre links, terminated onto SC connector outlets. The later projects used LC connectors.