Veolia Three Valleys Water
Summary
Cabling of building
Location
Hatfield Business Park, Hatfield
Systems
Molex PowerCat 6 UTP Cat6
Start & Finish
Nov 2008 – Jan 2009
Project Description
Veolia Water (formally Three Valleys Water) consolidated their offices into the new HUB building in Hatfield, a building to house 750 office staff.
Able Data were contracted by Como to install a 3,000 outlet Cat6 data cabling system. Run over four floors, outlets were terminated in a grid of 8-way consolidation points installed under the false floor. Desk outlets were connected to the consolidation points through solid patch lead connections.
The project was completed over a period of two months.
Download ![]() | Date | Notes |
|---|---|---|
| Veolia Water | 2008/2009 | 202 KB |
Dedicated software is required to view PDF files. Your computer may already have PDF viewing software installed; it may have been included with your Web browser or operating system. If you do not have it already, you will need to download and install the PDF viewing software of your choice in order to view the PDF files on this site. | ||