Veolia Three Valleys Water

Summary
Cabling of building

Location
Hatfield Business Park, Hatfield

Systems
Molex PowerCat 6 UTP Cat6

Start & Finish
Nov 2008 – Jan 2009

Project Description
Veolia Water (formally Three Valleys Water) consolidated their offices into the new HUB building in Hatfield, a building to house 750 office staff.

Able Data were contracted by Como to install a 3,000 outlet Cat6 data cabling system. Run over four floors, outlets were terminated in a grid of 8-way consolidation points installed under the false floor. Desk outlets were connected to the consolidation points through solid patch lead connections.

The project was completed over a period of two months.

Download DateNotes
Veolia Water2008/2009202 KB
Dedicated software is required to view PDF files. Your computer may already have PDF viewing software installed; it may have been included with your Web browser or operating system. If you do not have it already, you will need to download and install the PDF viewing software of your choice in order to view the PDF files on this site.