White & Case

Summary
Cabling of White & Case's new building in Lion Plaza.

Systems
SYSTIMAX GigaSPEED XL7 Cat6

Project Description
White & Case, a leading international law firm, moved their headquarters to Lion Plaza.

As part of the fit out of the refurbished building, Able Data supplied and installed 6,000 outlets over four floors. The core installation of horizontal connections was completed within five weeks, thanks to the use of pre-termination. This involved the manufacture and test of 3-way cable loom bundles in the factory, allowing a rapid installation on site. All RJ45 patch panels are of the SYSTIMAX fleximax variety, where standard outlet modules are clipped into the panel.

The project also involved the supply installation of 25 Meridian equipment cabinets and 18 Meridian HDPF's (high density patching frames).